-5 -5 Preparation of thermal fluid heater for inspection and test

The exact 46 CFR §61.30-5 text, rendered cleanly with its subsection structure — plus how this rule shows up on the exam.

Public-domain federal text · ingested from eCFR
Every answer cited & verifiedAll 4 USCG exam modulesReviewed by a former NMC exam writer

TL;DR

For visual inspection, access plates and manholes must be removed as required by the marine inspector and the heater and combustion chambers must be thoroughly cooled and cleaned.

Section 61.30-5 — full text

Rendered cleanly from the source — the exact regulatory text, with subsection structure preserved.

For visual inspection, access plates and manholes must be removed as required by the marine inspector and the heater and combustion chambers must be thoroughly cooled and cleaned. [CGD 80-064, 49 FR 32193, Aug. 13, 1984, as amended by CGD 95-027, 61 FR 26002, May 23, 1996; USCG-2020-0634, 89 FR 50189, June 12, 2024]

From regulation to exam

See how this section shows up on the test

Test your knowledge

Try 5 real exam questions on the rules behind this regulation — no sign-up needed.

Was this page helpful?

Start drilling in 30 seconds. Free.

No signup, no credit card — answer 5 real, cited exam questions right now.

46 CFR §61.30-5 — -5 -5 Preparation of thermal fluid heater for inspection and test · CaptainsGround