When a fire occurs in a machinery space aboard a small vessel, which combination of actions is required before activating the fixed extinguishing system?

  1. Shut off fuel supply and ventilation systemCorrect
  2. B. Deenergize all electrical systems vessel-wide and close all watertight doors
  3. C. Maneuver the vessel into the wind and notify the Coast Guard
  4. D. Don immersion suits and prepare survival craft for launching

Why A is correct

Both 46 CFR §28.265(d)(9)(iv) and 46 CFR §185.512(a)(3)(iv) specify that for a machinery space fire, the mariner must shut off the fuel supply and ventilation system before activating the fixed extinguishing system. Deenergizing the affected space's electrical system is a separate step; deenergizing the entire vessel is not specified.

More Firefighting procedures aboard small vessels questions

Start drilling in 30 seconds. Free.

No signup, no credit card — answer 5 real, cited exam questions right now.

When a fire occurs in a machinery space aboard a small vessel, whic… — USCG Exam Practice · CaptainsGround