A towline rigged for towing astern is found to have wire clips installed at its end as a permanent termination. Under 33 CFR §164.74, this rigging is:

  1. AAcceptable provided five or more wire clips are used with a thimble
  2. BAcceptable only if the towline is synthetic fiber
  3. CNot acceptable; wire clips are only permitted for temporary repair✓ correct
  4. DAcceptable if approved by a classification society authorized under §157.04

Why C is correct

33 CFR §164.74(a)(2)(iii) requires each towline to be free of wire clips except for temporary repair. For temporary repair, a thimble and at least five wire clips (or the manufacturer's specified number, whichever is more) are required. Wire clips are not a permitted permanent termination method.

Drill more Load line and tonnage basics questions

Every CaptainsGround answer cites the rule it tests — verified, not guessed. Try a free 5-question drill, no sign-up.

More practice questions

A towline rigged for towing astern is found to have wire clips inst… — USCG Exam Practice · CaptainsGround