Under 46 CFR §11.402, when does a calculated tonnage limitation result in the issuance of an unlimited tonnage endorsement rather than a limited one?

  1. A. When the applicant has served on vessels of 1,600 GRT or more for at least 12 months
  2. When the calculated limitation equals or exceeds 10,000 GRTCorrect
  3. C. When at least 50 percent of required experience is on vessels of 1,600 GRT or more
  4. D. When the calculated limitation equals or exceeds 5,000 GRT

Why B is correct

46 CFR §11.402(b) states that when the calculated tonnage limitation equals or exceeds 10,000 GRT, the applicant is issued an unlimited tonnage endorsement rather than a limited one.

More Load line and tonnage basics questions

Start drilling in 30 seconds. Free.

No signup, no credit card — answer 5 real, cited exam questions right now.

Under 46 CFR §11.402, when does a calculated tonnage limitation res… — USCG Exam Practice · CaptainsGround