A wet exhaust pipe on a small passenger vessel passes through a watertight bulkhead. According to 46 CFR §182.430, how must the watertight integrity of that bulkhead be maintained?

  1. A. Noncombustible packing must be used in the bulkhead penetration gland
  2. The pipe may be welded to a steel or equivalent bulkhead, or fiberglassed to a fiberglass reinforced plastic bulkhead with suitable expansion stress reliefCorrect
  3. C. A flexible metallic hose section must be installed on each side of the bulkhead penetration
  4. D. The pipe must be Schedule 80 material at the penetration point and double clamped

Why B is correct

46 CFR §182.430(f) states that a wet exhaust pipe may be welded to a steel or equivalent bulkhead, or a fiberglass wet exhaust pipe may be fiberglassed to a fiberglass reinforced plastic bulkhead, provided suitable arrangements are made to relieve expansion stresses. Noncombustible packing in the gland is the requirement for dry exhaust systems, not wet.

More Engine-room safety and hazardous materials questions

Start drilling in 30 seconds. Free.

No signup, no credit card — answer 5 real, cited exam questions right now.

A wet exhaust pipe on a small passenger vessel passes through a wat… — USCG Exam Practice · CaptainsGround