Under 46 CFR, what is the minimum pipe schedule required for discharge piping from fuel oil service pumps to boiler burners?

  1. A. Schedule 40
  2. B. Schedule 60
  3. Schedule 80Correct
  4. D. Schedule 160

Why C is correct

46 CFR §56.50-65(a) specifies that all discharge piping from fuel oil service pumps to burners must be seamless steel with a thickness of at least Schedule 80. Lighter schedules do not meet this requirement.