Prior to installation aboard ship, which of the following piping system diagrams must be submitted for Coast Guard approval under 46 CFR §56.01-10?

  1. A. Potable water distribution piping only
  2. Fuel oil service, transfer, and filling pipingCorrect
  3. C. Crew accommodation ventilation ducting
  4. D. Galley exhaust hood piping

Why B is correct

46 CFR §56.01-10(c)(1)(iv) requires that diagrams of fuel oil service, transfer, and filling piping be submitted for approval prior to installation. Potable water distribution, accommodation ventilation, and galley exhaust are not listed in that section.

More Pumps, valves, and piping systems questions

Start drilling in 30 seconds. Free.

No signup, no credit card — answer 5 real, cited exam questions right now.

Prior to installation aboard ship, which of the following piping sy… — USCG Exam Practice · CaptainsGround