According to 46 CFR §56.50-30, feed piping from the boiler to and including the required stop and stop-check valves must have a design pressure exceeding the maximum allowable working pressure (MAWP) of the boiler by which of the following amounts?

  1. A. 10 percent or 100 psig, whichever is less
  2. 25 percent or 225 psig, whichever is lessCorrect
  3. C. 25 percent or 225 psig, whichever is greater
  4. D. 50 percent or 500 psig, whichever is less

Why B is correct

46 CFR §56.50-30(a)(3) states that feed piping from the boiler to and including the required stop and stop-check valves must have a design pressure exceeding the boiler MAWP by either 25 percent or 225 psig, whichever is less. The 'whichever is greater' option is a common distractor but is incorrect. (46 CFR §56.50-30)

More Boiler and steam propulsion fundamentals questions

Start drilling in 30 seconds. Free.

No signup, no credit card — answer 5 real, cited exam questions right now.

According to 46 CFR §56.50-30, feed piping from the boiler to and i… — USCG Exam Practice · CaptainsGround