Under 46 CFR §56.50-30, feed pumps for water-tube boilers are restricted regarding their water supply connections. A vessel's chief engineer proposes connecting a water-tube boiler feed pump to both the freshwater system and the saltwater fire main as a backup supply. Which statement correctly evaluates this proposal?

  1. A. The proposal is acceptable provided a stop-check valve is fitted between the saltwater connection and the pump suction
  2. The proposal is not permitted; 46 CFR §56.50-30(a)(4) requires feed pumps for water-tube boilers to have freshwater connections onlyCorrect
  3. C. The proposal is acceptable because 46 CFR §56.50-30 requires two separate means of feedwater supply, and the saltwater connection satisfies the second means
  4. D. The proposal is acceptable only if the saltwater connection is used exclusively as an emergency measure and is documented in the vessel's SMS

Why B is correct

46 CFR §56.50-30(a)(4) explicitly states that feed pumps for water-tube boilers must have freshwater connections only. Connecting a saltwater supply to a water-tube boiler feed pump is prohibited regardless of valve arrangements, emergency intent, or SMS documentation. Saltwater would introduce chlorides and cause severe scaling and corrosion. (46 CFR §56.50-30)

More Boiler and steam propulsion fundamentals questions

Start drilling in 30 seconds. Free.

No signup, no credit card — answer 5 real, cited exam questions right now.

Under 46 CFR §56.50-30, feed pumps for water-tube boilers are restr… — USCG Exam Practice · CaptainsGround