According to the recommended emergency instructions, which tool may be aligned to serve as a bilge pump during a flooding emergency?

  1. A. The anchor windlass hydraulic system
  2. B. The fire main pressure relief valve
  3. The fire pumpCorrect
  4. D. The fuel transfer pump

Why C is correct

46 CFR §185.512(a)(1)(iii) specifically states that fire pumps should be aligned to use as a bilge pump if possible during a flooding emergency. No other pump is identified for this purpose in the recommended emergency instructions.