Before opening a pressurized system, valve, or casing in the engine room, which sequence of conditions must the watchstander verify?

  1. System is isolated, depressurized, cooled, and where required tagged outCorrect
  2. B. System is depressurized and the watch engineer has been notified
  3. C. System is tagged out and the chief engineer has given verbal authorization
  4. D. System is cooled and the engineering log entry has been completed

Why A is correct

NAVEDTRA 14104 §1-2 explicitly states that before opening any pressurized system, valve, or casing, the watchstander verifies it is isolated, depressurized, cooled, and, where required, tagged out. All four conditions are required; omitting any one of them creates a hazard not addressed by the other three alone.

More Watch duties, terminology, and instrumentation questions

Start drilling in 30 seconds. Free.

No signup, no credit card — answer 5 real, cited exam questions right now.

Before opening a pressurized system, valve, or casing in the engine… — USCG Exam Practice · CaptainsGround