Under 46 CFR §63.01-3, an automatic auxiliary boiler with a heat input rating of 14,000,000 Btu/hr must meet the requirements of which subchapter for its construction, and which part for its control system?

  1. A. Part 63 for construction; part 62 for controls
  2. Part 52 for construction; part 62 for controlsCorrect
  3. C. Part 52 for construction; part 63 for controls
  4. D. Part 63 for construction; part 63 for controls

Why B is correct

46 CFR §63.01-3(b) states that automatic boilers with heat input ratings of 12,500,000 Btu/hr (3.66 megawatts) and above must meet the requirements of part 52 of the subchapter, and their control systems must meet the requirements of part 62. A 14,000,000 Btu/hr boiler exceeds the 12,500,000 Btu/hr threshold, so part 63 does not govern its construction or controls. (46 CFR §63.01-3)

More Boiler and steam propulsion fundamentals questions

Start drilling in 30 seconds. Free.

No signup, no credit card — answer 5 real, cited exam questions right now.

Under 46 CFR §63.01-3, an automatic auxiliary boiler with a heat in… — USCG Exam Practice · CaptainsGround