USCG Exam PracticeEmergency duties — MOB, towing, and care of survivors
Under 46 CFR §28.265(d)(6), which action is specified for managing bilge water during rough weather or when crossing a hazardous bar, in addition to using a power-driven bilge pump?
- A. Activate the fixed fire-suppression system to pressurize the bilge space
- B. Open all sea cocks to equalize internal and external water pressure
- ✓ Use a hand pump and buckets, and align fire pumps to serve as bilge pumps if possibleCorrect
- D. Transfer fuel to the centerline tank to lower the center of gravity before dewatering
Why C is correct
46 CFR §28.265(d)(6)(ii) and (iii) specify using a power-driven bilge pump, hand pump, and buckets to dewater, and aligning fire pumps to serve as bilge pumps if possible. Opening sea cocks or activating fixed suppression systems are not listed and would be contrary to damage-control principles.
Cited:46 CFR §28.265