On a cargo winch or deck crane, what must the brake be capable of doing if power or control is lost?

  1. Automatically holding the rated loadCorrect
  2. B. Slowly lowering the load to the deck at a controlled rate
  3. C. Triggering the overload cut-out before the load is released
  4. D. Engaging the limit switch to stop all hoist motion

Why A is correct

Per NAVEDTRA 14343 §9-4, cargo winch brakes must hold the rated load automatically when power or control is lost. Controlled lowering, overload cut-outs, and limit switches are separate safety features and do not substitute for this brake requirement.

More Deck machinery and ground tackle questions

Start drilling in 30 seconds. Free.

No signup, no credit card — answer 5 real, cited exam questions right now.

On a cargo winch or deck crane, what must the brake be capable of d… — USCG Exam Practice · CaptainsGround