Under 46 CFR §28.335, each integral fuel tank vent pipe must terminate in what configuration on the weather deck?

  1. AA 90-degree bend fitted with a flame screen
  2. BA 135-degree bend fitted with a check valve
  3. CA 180-degree bend fitted with a flame screen✓ correct
  4. DA straight open pipe fitted with a pressure relief valve

Why C is correct

46 CFR §28.335(d)(1) requires each fuel tank vent pipe to be connected to the highest point of the tank, terminate in a 180-degree bend on a weather deck, and be fitted with a flame screen. The same requirement appears in 46 CFR §28.835(b).