During a biennial proof load test of cargo gear, once the load has been lifted, what additional action is required before the test is considered complete?

  1. A. The load must be held stationary for a minimum of 10 minutes
  2. The load must be swung as far as possible in both directionsCorrect
  3. C. The load must be lowered and re-lifted three times
  4. D. The load must be transferred to a second boom for cross-testing

Why B is correct

46 CFR §28.885(c) requires that after the load is lifted, it shall be swung as far as possible in both directions as part of the proof load test procedure.

More Deck equipment — winches, capstans, windlasses questions

Start drilling in 30 seconds. Free.

No signup, no credit card — answer 5 real, cited exam questions right now.

During a biennial proof load test of cargo gear, once the load has… — USCG Exam Practice · CaptainsGround