Before paralleling an incoming generator to the bus, the operator uses a synchroscope and frequency meter together. At what position of the synchroscope pointer should the breaker be closed?

  1. A. As the pointer passes through the six o'clock (180°) position, indicating opposite phase
  2. As the pointer creeps slowly through the twelve o'clock (in-phase) positionCorrect
  3. C. At any position, provided the frequency meters show identical readings
  4. D. As the pointer accelerates through the three o'clock position to allow for breaker closing time

Why B is correct

The synchroscope and frequency meter are used together to match frequency and phase before paralleling. The breaker is closed only as the synchroscope creeps slowly through its in-phase, twelve o'clock position. Closing at any other position risks a severe out-of-phase connection.

More Hand/power tools, measuring instruments, and maintenance questions

Start drilling in 30 seconds. Free.

No signup, no credit card — answer 5 real, cited exam questions right now.

Before paralleling an incoming generator to the bus, the operator u… — USCG Exam Practice · CaptainsGround