Before paralleling an incoming generator to the bus, the operator uses the synchroscope and frequency meter together. The breaker should be closed at which point?

  1. A. When the synchroscope pointer is rotating rapidly clockwise, indicating the incoming machine is running fast
  2. B. When the frequency meter shows the incoming machine is exactly 1 Hz above bus frequency to ensure it picks up load immediately
  3. As the synchroscope pointer creeps slowly through the in-phase (twelve o'clock) positionCorrect
  4. D. When the power-factor meter reads unity, regardless of synchroscope position

Why C is correct

NEETS Mod. 3 §1-4 states that before paralleling generators the operator uses the frequency meter and synchroscope together to match frequency and phase, closing the breaker only as the synchroscope creeps slowly through its in-phase (twelve o'clock) position. Closing at any other position causes a damaging out-of-phase connection.

More Hand/power tools, measuring instruments, and maintenance questions

Start drilling in 30 seconds. Free.

No signup, no credit card — answer 5 real, cited exam questions right now.

Before paralleling an incoming generator to the bus, the operator u… — USCG Exam Practice · CaptainsGround