Under 46 CFR §58.30-5, a pneumatic system with a maximum allowable working pressure exceeding 150 psi must be designed with which of the following?

  1. A. A fusible plug or bursting disc on each receiver
  2. A surge tank or other acceptable means of pulsation dampeningCorrect
  3. C. An intercooler between each compression stage
  4. D. A moisture separator on the compressor discharge

Why B is correct

46 CFR §58.30-5(c) specifically requires that pneumatic systems with a maximum allowable working pressure in excess of 150 psi be designed with a surge tank or other acceptable means of pulsation dampening. Fusible plugs, intercoolers, and moisture separators are all legitimate pneumatic system components but are not the requirement stated in §58.30-5(c) for systems above 150 psi.

More Hydraulics and pneumatics questions

Start drilling in 30 seconds. Free.

No signup, no credit card — answer 5 real, cited exam questions right now.

Under 46 CFR §58.30-5, a pneumatic system with a maximum allowable… — USCG Exam Practice · CaptainsGround