Under 46 CFR §28.335, an integral fuel tank vent pipe must terminate on the weather deck with what type of fitting, and in what configuration?

  1. A. A 90-degree bend fitted with a check valve
  2. A 180-degree bend fitted with a flame screenCorrect
  3. C. A 90-degree bend fitted with a flame screen
  4. D. A 180-degree bend fitted with a check valve

Why B is correct

46 CFR §28.335(d)(1) requires each fuel tank vent pipe to terminate in a 180-degree bend on a weather deck and be fitted with a flame screen. A check valve is not specified; the flame screen is the required fitting.

More Fueling procedures and pollution prevention questions

Start drilling in 30 seconds. Free.

No signup, no credit card — answer 5 real, cited exam questions right now.

Under 46 CFR §28.335, an integral fuel tank vent pipe must terminat… — USCG Exam Practice · CaptainsGround