Under 46 CFR §182.430, when a wet exhaust pipe must pass through a watertight bulkhead, which of the following statements is correct?

  1. A. Noncombustible packing must be used in the bulkhead penetration gland regardless of pipe material
  2. The watertight integrity of the bulkhead must be maintained, and a fiberglass wet exhaust pipe may be fiberglassed to a fiberglass reinforced plastic bulkhead if suitable arrangements relieve expansion stressesCorrect
  3. C. The pipe must be welded to a steel bulkhead in all cases
  4. D. A flexible metallic hose section must be installed on each side of the bulkhead penetration

Why B is correct

46 CFR §182.430(f) requires that watertight integrity be maintained at bulkhead penetrations, and specifically permits a fiberglass wet exhaust pipe to be fiberglassed to a fiberglass reinforced plastic bulkhead provided suitable arrangements relieve expansion stresses. Noncombustible packing in penetration glands applies to dry exhaust systems, not wet.

More Engine-room safety and hazardous materials questions

Start drilling in 30 seconds. Free.

No signup, no credit card — answer 5 real, cited exam questions right now.

Under 46 CFR §182.430, when a wet exhaust pipe must pass through a… — USCG Exam Practice · CaptainsGround