Before cutting wire rope, the correct preparatory step is to:

  1. Apply seizings on both sides of the intended cutCorrect
  2. B. Lubricate the wire at the cut point to ease strand separation
  3. C. Unlay the strands one lay length back from the cut
  4. D. Inspect for broken wires within one lay length of the cut

Why A is correct

Both NAVEDTRA 14067 §3-4 and NAVEDTRA 14343 §8-1 specify that seizings must be applied on both sides of the cut before cutting wire rope so the strands cannot fly apart or unlay.